CASE STUDY | BIORETENTION BASIN AT GATTON CORRECTIONAL CENTRE
07 May 2020
Total Environmental Concepts has specialised in environmental landscaping and maintenance for over 40 years. The team recently used its expertise to solve environmental concerns posed at a bioretention basin at Gatton Correctional Centre, QLD.
Total Environmental Concepts (TEC) has over 40 years of experience in the land management industry. Specialising in environmental landscaping and maintenance, TEC is comprised of a professional team that provides knowledgeable advice, skilled services and valuable assistance across a varied range of rehabilitation, construction and maintenance operations.
TEC was contracted to provide its services for the bioretention basin at Gatton Correctional Centre in QLD.
On inspection, the basin had several major issues that required analysis and a solution.
BASIN
There was an extensive amount of weeds blocking the batter. The solution was to spray the weeds or remove by hand.
TEC used a forestry mulcher to create maintenance access down the batter to the bioretention. This involved:
- Clearing any trees on access alignment (regrowth only)
- Clearing vegetation and removing any sediment/debris from the surface of the bioretention system including ground covers and dispose
- Removal of vegetation on the batters was required for removal of lantana and other weedy material
On completion, batters were mulched and replanted with jute netting to high water level, to protect the embankment during the establishment phase.
Before
After
FILTER MEDIA WASHOUT AT THE OUTLET GABIONS
The downstream end of the bioretention has a wall of gabions through which the underdrainage has been placed. The gabions form the end of the bioretention and a bentonite liner has been installed between the filter media and gabion. The design is poor and has resulted in washout of the filter media through the gabions and the creation of a number of large holes.
The solution was to create a barrier upstream of the outlet gabions. A range of options were available with the potential cheapest solution as per below:
- Excavate the area upstream of the gabions for a distance of 2m. Excavation to extent 500mm into in-situ soils below filter media. Care to preserve underdrainage pipes.
- Place well grade suitable clay fill and compact including around underdrain pipes.
- Line the upstream surface of the fill material with Geofabric (Bidim A24) and install bioretention drainage layer, transition layer and filter media and compact.
- Install 100-230mm rock mattress to the surface of fill material over Geofabric (Bidim A24) and tie into existing gabions.
Before
After
EROSION AROUND ENDS OF GABION WEIR
The gabion weir was not properly extended up the batter to the natural ground (the weir was not been properly keyed in). The result is an erosion scour around both ends of the gabion weir.
The solution:
- Repair scour at the ends of the gabion weir and place rock scour protection (100-230m rock mattress) to up the batter to tie in with existing levels.
- The gabion wall was extended to a solid embankment than an additional gabion basket was added on top of the existing wall on each end to control and divert the water to the centre of the overflow of the gabion wall.
- Compact additional clay on the embankment, place Geofabric (Bidim A24) and rock guard with 100- 230mm rock mattress to surface to protect embankment.
Before
After
VEGETATION COVER
Following extensive storm damage from rain in 2020, there were large washouts in the basin’s drainage media occurred, requiring the removal of all existing vegetation and the importing of 100 cubic meters of filter media to repair basin.
TEC undertook mulching, jute netting and replanting of the basin in accordance with the Construction & Establishment Guidelines for Vegetation Stormwater Systems, including the use of fertiliser and water crystals in planting holes. Planting numbers are based on planting 50 percent of a 1700 m2 area.
The solution is to install a temporary irrigation system from the site irrigation system or directly from the pond. At the end of three months, a review will be undertaken to consider whether further establishment is required. The bioretention will need to achieve the requirements (i.e. plant coverage, maturity) outlined by the measurement of success in the Construction & Establishment Guidelines for Vegetation Stormwater Systems.
Flush all underdrainage pipes to ensure they are clean and draining.
Contact TEC via the links below to help with your next project.